Projects
MISSION ROCK DESIGN & MISSION ROCK PARCEL A
Location:
1051 3rd Street Block A
San Francisco, CA
​
General Contractor:
Swinerton
Contractor:
Critchfield Mechanical, Inc.
Scope:
Provided labor and materials for the piping phase of the project.
​
MISSION ROCK BLOCK F
Location:
1051 3rd Street Block F
San Francisco, CA
​
General Contractor:
Webcor Builders
Contractor:
Critchfield Mechanical, Inc.
Scope:
HVAC labor, material purchase, and HVAC test and balance for the A/C system.
Photo Source: www.sfpuc.gov
SOUTHEAST WATER POLLUTION CONTROL PLANT NEW HEADWORKS FACILITY
Location:
750 Phelps Street
San Francisco, CA
​
General Contractor:
Sundt Construction [Joint Venture]
Contractor:
Western Water Constructors, Inc.
Scope:
Processed pipe and pipe rack steel (Scope II).
1450 OWENS STREET
Location:
1450 Owens Street
San Francisco, CA
​
General Contractor:
Truebeck Construction
Contractor:
Critchfield Mechanical, Inc.
Scope:
Provided plumbing labor, and purchased equipment and materials.
socksite.com
SOUTHEAST WATER POLLUTION CONTROL PLANT BIOSOLIDS DIGESTER FACILITIES
Location:
San Francisco, CA​
​
General Contractor:
MWH Constructors & Webcor Builders
Contractor:
Broadway Mechanical-Contractors, Inc.
Scope:
Provided project management, plumbing and pipe installation services for Bldg. 600 & 610.
921 HOWARD STREET
Location:
921 Howard Street
San Francisco, CA
​
General Contractor:
Swinerton
Contractor:
O’Brien Mechanical Inc. II
Scope:
Provided fuel oil piping installation.
Photo Source: www.tndc.org
2150 Webster Street, via Google Street View
BART HQ
Location:
2150 Webster Street
Oakland, CA 94612
​
Public Agency:
Bay Area Rapid Transit
Prime Contractor:
Turner Construction
Contractor:
Broadway Mechanical Contractor, Inc.
Scope:
HVAC wet and dry side installation
plumbing wet and dry side installation.
SEWPCP New Headworks
Facility Construction
Location:
750 Phelps Street
San Francisco, CA 94124
​
City Agency:
San Francisco Public Utilities Commission
Contractor:
Sundt/Walsh, A Joint Venture
Scope:
Provided all labor, material, equipment, services, supervision, and supplies to perform the temporary south channel bypass piping installation.
socksite.com
5M M2 Residential Development
Location:
434 Minna Street
San Francisco, CA 94103
​
General Contractor:
Build Group, Inc.
Contractor:
Critchfield Mechanical, Inc.
Scope:
HVAC wet & dry side installation.